The Town is continuing with the implementation of the Inflow and Infiltration Phase 1 Report. The Town’s contractor, Insituform Technologies, Inc., will be cleaning and performing CCTV of the sanitary gravity sewer mains throughout the Town. This work will be completed using a no-dig, trenchless technology. The length of time the contractor will be working on any one street will vary depending on the length of pipe to be cleaned. The contractor will be working on the streets indicated below between December 6, 2021 and December 10, 2021. To minimize road closures, please refrain from parking on the following streets per designated dates below:
• Wells Road, Monday December 6, 2021 and Tuesday December 7, 2021
• Dunbar Road, Wednesday December 8, 2021 and Thursday December 9, 2021
• Atlantic Ave, Friday December 10, 2021
If you have any questions or concerns please contact Jane House, Project Engineer for the Town at (561) 838-5440.